Bench blasting operation on limestone opencast mining at PT. Semen Padang (Persero), Indonesia performed by electric blasting using coloumn loading system. Limestone deposit consist of three type of rock characteritics that are hard limestone, sugary limestone, and jointed limestone. In general, a good blasting design should implementing subdrilling to avoid toe. In this case of study the subdrilling is not need due to the present of many cracks caused by basalt intrusion. Blasting geometry that applied to blast the jointed limestone resulting blasting fragmentation that commonly relatively small in size (<60 cm) but still has some boulders (>60 cm) that caused by coloumn loading system where energy was concentrated in the bottom. Based on field observation of limestone blasting operation and productivity of excavator being used that is Excavator Hitachi EX 1100 with 5.4 m3 bucket capacity, can be optimized. Especially from the view of drilling and blasting efficiency by modifying blasting geometry and explosive usage to optimize fragmentation to the productivity of excavator being used. Modification that performed is eliminate the sub drilling and change the explosives loading system from coloumn loading to deck loading (include amount of explosives and detonator being used). Based on result of modification, achieve decreasing of boulder percentage as much as 50.25% that is from 9.71% to 4.83% and increasing of excavator productivity up to 36.10% from 1,479 ton/hour to 2,013 ton/hour as well as decreasing blasting cost up to 17.18% from Rp 3,456/ton to Rp 2,862/ton.
Creative Commons License

This work is licensed under a Creative Commons Attribution 4.0 International License.

Authors who publish with this journal agree to the following terms:

    1. Authors retain copyright and grant the journal right of first publication with the work simultaneously licensed under a Creative Commons Attribution License that allows others to share the work with an acknowledgement of the work's authorship and initial publication in this journal.
    2. Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this journal.
    3. Authors are permitted and encouraged to post their work online (e.g., in institutional repositories or on their website) prior to and during the submission process, as it can lead to productive exchanges, as well as earlier and greater citation of published work (See The Effect of Open Access).