Risk in Government’s Estimate for Toll Road: Based on Investors’ Perspective

Reini D. Wirahadikusumah (1), - Sapitri (2), Betty Susanti (3), Biemo W. Soemardi (4)
(1) Department of Civil Engineering, Institut Teknologi Bandung, Bandung, 40132, Indonesia
(2) Department of Civil Engineering, Universitas Islam Riau, Pekanbaru, 28284, Indonesia
(3) Department of Civil Engineering, Universitas Sriwijaya, Inderalaya, 30622, Indonesia
(4) Department of Civil Engineering, Institut Teknologi Bandung, Bandung, 40132, Indonesia
Fulltext View | Download
How to cite (IJASEIT) :
Wirahadikusumah, Reini D., et al. “Risk in Government’s Estimate for Toll Road: Based on Investors’ Perspective”. International Journal on Advanced Science, Engineering and Information Technology, vol. 8, no. 2, Mar. 2018, pp. 475-82, doi:10.18517/ijaseit.8.2.4322.
The government’s estimate for toll road concession award, as a comparator for investors’ bids, has been criticized by investors, as it does not fully include the proper cost of risks. Thus, there is a need to develop a more equitable estimate that considers the risks, both at the project and at the business/corporate level. The study was mainly supported by qualitative data on the probability of occurrences and impact assessment of risks, acquired through interviews with major investors. Probability Impact Matrices were used to identify risks categorized as “high risks.” Findings have indicated that the high and dominant risks are: i) Route/traffic management (lower traffic volume due to changing routes); ii) Overloading (poorly imposing the limitations of heavy vehicles); and iii) Inadequate/inaccurate data in feasibility study documents. Recommendation on the mitigation plan for these risks has been corroborated by both parties, the government, and the investors. Parts of the risk are proposed to be incorporated into the government’s estimate, while other risks should be adequately addressed in specific contract clauses for Indonesia’s PPP scheme.

Ministry of Public Works Regulation. Strategic Planning for 2010-2014, pp. 89-104. 2010.

S. F. Rostiyanti, “Performance assessment framework for toll road implementation by using public private partnership in Indonesia,” Jurnal Teknik Sipil., vol. 11, no. 2, pp. 117-127. 2012.

B. S. Soedjito, Develop Public Private Partnership, PPP Magazine. Ed. 12- December 2009 - January 2010, pp. 8-9.

Wirahadikusumah, B. Susanti, Safitri, and B. Soemardi, “Concession Award For Indonesian Toll Roads - A Comparison Analysis”, in Proc. International Structural Engineering and Construction Conference, vol. II. 2013, pp. 1591-1596.

Ministry of Public Works Regulation No. 13/PRT/M/2010 on Guidelines for Toll Road Concession Award, Jakarta, 2010.

C. Hardcastle, “The private finance initiative-friend or foe,” in Proc. International Conference in the Built Environment in the 21st Century, 2006, pp. 3-13.

Y. H. Suseno, M. A. Wibowo, B. H. Setiadji, “Risk analysis of BOT scheme on post-construction toll road”, in Proc. The 5th International Conference of Euro Asia Civil Engineering Forum, 2015, pp. 117-123.

R. D. Wirahadikusumah, Sapitri, B. Susanti, and B. Soemardi, Risk Inclusion in the Reserve Price Estimation for Toll Road Concession Award. Journal of Traffic and Logistics Engineering, vol. 2, no. 1, pp. 34-39, 2014.

D. Widiantono, “Development of risk’s analysis method for toll road investment,” Final Report of Research and Development Agency - Ministry of Public Works, Bandung, 2003.

Winarsa, A. J. Dwi. “Risk Management in Construction Contract: Case Study on Toll Road Cikampek - Purwakarta - Padalarang Phase II,” M. Eng. thesis, University of Indonesia, Jakarta, 2005.

S. Naimah, “Study of Public Private Partnership Implementation on Toll Road Sector in Indonesia: Case Study on Toll Road Solo - Kertosono,” M. Eng. thesis, Institut Technology of Bandung, Indonesia, 2009.

F. A. Nadia, “Risk and Policy in Indonesian Toll Road Development: from the Perception of Public and Private Sector Study Case of Pandaan - Malang & Manado Bitung,” M. Eng. Thesis, Institute of Social Studies, Netherlands, 2016.

M. Bull, A. Mauchan, and L. Wilson, (2017), Toll Road PPPs: Indentify, Mitigating and Managing Traffict Risk, homepage on Publict Private Infrastructure Advisory Facility and The Global Infrastructure Facility (PPIP). [Online]. Available: https://ppiaf.org/documents/5348?ref_site=ppiaf.

D. Cooper, S. Grey, G. Raymond, and P. Walker, Project Risk Management Guidelines: Managing Risk in Large Projects and Complex Procurement, England, John Wiley & Sons Ltd, 2005.

I. Mahani, R. Z. Tamin, K. S. Pribadi, and A. Wibowo, “Evaluation of Implementation Viability Gap Funding (VGF) Policy on Toll Road Investment in Indonesia,” in Proc. The 3rd International Conference on Construction and Building Engineering, 2017.

Presidential Regulation No.38/2015 on Cooperation between Government and Business Entities in the Provision of Infrastructure. Jakarta, 2015.

Ministry of National Development Planning Regulation No.4/2015 on Procedures for implementation of cooperation between government and business entities in the provision of infrastructure. Jakarta, 2015.

Regulation of Procurement Agency Goods/ Services No.19/2015 on Procurement Procedures of Government Enterprises Cooperation with Business Entities in Infrastructure Provision, Jakarta, 2015.

Presidential Regulation No. 67/2005 on Cooperation between Government and Business Entities in the Provision of Infrastructure. Jakarta, 2005.

Ministry of Finance Republic Indonesia, Finance Minister Regulation No.170/PMK.08/2015, Jakarta, 2015.

J. Smith, R. Satar, A. Wiryawan, “Indonesian Infrastructure Stable foundations for growth,” The second edition of PwC’s annual Indonesian infrastructure report, 2016.

Creative Commons License

This work is licensed under a Creative Commons Attribution 4.0 International License.

Authors who publish with this journal agree to the following terms:

    1. Authors retain copyright and grant the journal right of first publication with the work simultaneously licensed under a Creative Commons Attribution License that allows others to share the work with an acknowledgement of the work's authorship and initial publication in this journal.
    2. Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this journal.
    3. Authors are permitted and encouraged to post their work online (e.g., in institutional repositories or on their website) prior to and during the submission process, as it can lead to productive exchanges, as well as earlier and greater citation of published work (See The Effect of Open Access).